TL;DR
- Legal basis: Art. 21(2)(c) NIS2 Directive and, in identical wording, § 30(2) no. 3 BSIG: backup management, disaster recovery, crisis management
- Not a statutory term: "DR plan", RTO and RPO do not appear in the law — the DR plan is the practice standard for evidencing the measures and their documentation (§ 30(1) BSIG)
- 8 plan sections: scope and activation, roles, scenarios, RTO/RPO matrix, recovery procedures, communications, tests, maintenance
- 5 typical scenarios: ransomware, data-centre outage, cloud outage, insider, natural event
- RTO/RPO in four tiers (practice example): Tier 1 (4 h / 15 min) to Tier 4 (1 week); the binding values are those from your business impact analysis
- Tests (practice recommendation): one focus test per quarter plus an annual full scenario with the crisis team — no statutory deadline
- Reports: significant security incident to the joint reporting office of BSI and BBK (24 h / 72 h / 1 month, § 32(1) BSIG), in parallel Art. 33 GDPR where applicable
- Fines in Germany: § 65 BSIG — up to EUR 10 million for particularly important entities, up to EUR 7 million for important entities
- Austria: the same obligation in § 32(4)(c) NISG 2026, applicable since 1 October 2026; reports go to the competent CSIRT
Main article: BCM under NIS2 — business impact analysis, emergency plan and crisis team. This page is the template for the technical part of it, the disaster recovery plan.
A disaster recovery plan (DR plan) describes how an entity restores IT systems, data and infrastructure after an emergency. This template shows a proven structure in eight sections, five typical scenarios, RTO/RPO values per service class and a test plan. The NIS2 guide gives the overall overview of the NIS2 obligations; further in-depth articles are in the NIS2 knowledge area.
1. What NIS2 Art. 21(2)(c) and § 30(2) no. 3 BSIG require
Art. 21(2)(c) of the NIS2 Directive reads: "business continuity, such as backup management and disaster recovery, and crisis management". § 30(2) no. 3 BSIG adopts this wording. The law thus names three elements:
- Backup management: documented backup strategy, regular backups, testing that data can be restored
- Disaster recovery: technical and organisational procedures for recovery
- Crisis management: crisis team, communications, decision and escalation paths
The standard is set by § 30(1) BSIG: the measures must be appropriate, proportionate and effective, and the entity must document compliance with them. The law does not expressly prescribe a "disaster recovery plan" or RTO and RPO values; the DR plan is, however, the usual practice standard for evidencing backup management and recovery. The addressees are particularly important and important entities; in Germany the BSIG has applied since 6 December 2025 (BGBl. 2025 I No. 301) without a general transition period; the obligations under § 30 BSIG have applied since then.
The DR plan implements the first two elements operationally and supports the third. It stands alongside the BCM plan, the backup concept and the incident response plan (handling of security incidents, § 30(2) no. 2 BSIG). How it fits into all ten areas of measures is shown in § 30 BSIG: 10 mandatory NIS2 measures.
Financial sector and energy: a different legal basis
For financial entities under Art. 2(2) of Regulation (EU) 2022/2554 (DORA), §§ 30, 31, 32, 35, 36, 38 and 39 BSIG do not apply (§ 28(6) no. 1 BSIG); their obligations on backup, recovery and crisis management follow not additionally but instead from DORA (Art. 11 and 12 of Regulation (EU) 2022/2554) — see NIS2 + DORA for banks and financial services. For operators of energy supply networks, energy installations or digital energy services under the Energy Industry Act who are subject to §§ 5c to 5e EnWG, §§ 30, 31, 32, 35, 36, 38, 39, 61 and 62 BSIG do not apply (§ 28(5) sentence 1 no. 2 BSIG), except where operating the energy installation is only an ancillary activity, where further critical installations are operated or where further activities of another entity type are carried out (§ 28(5) sentences 2 and 4 BSIG) — see NIS2 in energy supply.
Austria: the same obligation in the NISG 2026
Austria (AT): in Austria the NISG 2026 (BGBl. I No. 94/2025) applies instead of the BSIG. § 32(4)(c) NISG 2026 requires, in the same wording, "business continuity, such as backup management and disaster recovery, and crisis management". The obligation has applied since 1 October 2026 (§ 51(2) NISG 2026). The entity reports significant cybersecurity incidents to the competent CSIRT (§ 34(2) NISG 2026). The management bodies must ensure and supervise compliance with the risk management measures (§ 31 NISG 2026); the competent authority is the Federal Office for Cybersecurity (§ 3a(1) NISG 2026). The structure of this template also fits there; reporting channels and references need to be adapted. More in the article NIS2 Austria (NISG 2026).
2. DR plan structure
A DR plan that holds up to review contains the following eight sections. The structure is practice; the law prescribes no sections.
Section 1: Scope and activation
- Which systems, processes and sites are covered?
- Who activates the plan (crisis team, IT management, executive management)?
- Activation criteria with measurable thresholds (e.g. "outage > 4 h", "confirmed data exfiltration", "more than 5 encrypted servers")
- Alerting procedure: 24/7 reachability, escalation phone list
Section 2: Roles and responsibilities
- Crisis team: lead, deputy, members, reachability
- IT recovery team: owners per system cluster
- Communications owners (internal, supervisory authority, customers, media)
- External partners: IT forensics, law firm, PR agency, cyber insurer
Section 3: Scenarios
Per scenario: trigger, impact, immediate measures, recovery approach, specifics (see section 3 of this article).
Section 4: RTO/RPO matrix
Per service or application: tier classification, RTO, RPO, dependent systems, restart sequence.
Section 5: Recovery procedures
- Technical procedures (restore scripts, failover procedures, cloud failover)
- Dependency sequence (DNS → Active Directory → database → application)
- Validation tests after recovery
- Handover to normal operations
Section 6: Communications
- Internal communications: employees, works council
- Supervisory authority: the entity reports a significant security incident (§ 2 no. 11 BSIG) in stages (24 h / 72 h / 1 month, § 32(1) BSIG) to the joint reporting office of the Federal Office for Information Security (BSI) and the Federal Office of Civil Protection and Disaster Assistance (BBK); procedure and content: NIS2 incident reporting.
- Data protection: where personal data are affected, the notification to the data protection supervisory authority runs in parallel — without undue delay and, where feasible, within 72 hours of becoming aware, unless the breach is unlikely to result in a risk (Art. 33(1) GDPR). This also applies without data exfiltration, because loss or destruction of data is also a breach (Art. 4 no. 12 GDPR). Where a high risk is likely, the data subjects must additionally be informed (Art. 34(1) GDPR).
- Emergency communications independent of the failed infrastructure; § 30(2) no. 10 BSIG names, where appropriate, secured emergency communication systems within the entity
- Customers and contractual partners, media and the public (for major incidents)
- Prepared wording (holding statements)
Section 7: Tests and exercises
- Test plan with frequency per scenario
- Template for the test record
- Findings tracking and corrective-action plan
Section 8: Maintenance and updates
- Review cycle (practice recommendation: at least annually)
- Triggers for event-driven updates (personnel changes, new systems, lessons learned)
- Owners for maintenance
3. 5 typical scenarios in detail
Scenario 1: Ransomware attack
The trigger is the encryption of critical systems, often combined with data exfiltration. The recovery source is immutable backups, not potentially infected snapshots; the restart begins only after forensic clearance. Isolation, forensics, reports and a criminal complaint are described in the Ransomware Recovery 72h plan.
Scenario 2: Data-centre outage
- Trigger: fire, power outage beyond UPS capacity, water, cooling failure, physical damage
- Impact: complete outage of locally operated systems
- Immediate measures: failover to the secondary data centre, inform employees, notify service providers
- Recovery strategy: active-active cluster (hot standby) or active-passive (warm standby) with a documented failover procedure
- Specifics: access lockdown and evidence preservation where arson is suspected
Scenario 3: Outage of a cloud provider
- Trigger: outage of a cloud provider's infrastructure, email or collaboration services in the region used
- Impact: depends on the degree of dependency — from partial (email briefly unavailable) to total (full SaaS dependency)
- Immediate measures: check the provider's status page, own status communications, activate workarounds (e.g. local tools, telephone instead of video conference)
- Recovery strategy: multi-region with the same provider or multi-cloud across providers — document the cost-benefit trade-off
- Specifics: check the provider's SLA, document damages claims
The provider's perspective is described in the article NIS2 for cloud providers and SaaS.
Scenario 4: Insider attack or unauthorised access
- Trigger: malicious employees, compromised privileged accounts, unauthorised access
- Impact: data manipulation, data exfiltration, sabotage
- Immediate measures: lock accounts, engage forensics, involve the works council where employees are concerned (in the public sector the staff council), coordinate with law enforcement authorities
- Recovery strategy: restore manipulated data from backups with preserved integrity, analyse audit trails in full
- Specifics: employment-law measures, co-determination, evidence preservation while safeguarding employee data protection (in Germany additionally § 26 BDSG)
Scenario 5: Natural event or force majeure
- Trigger: flood, storm, earthquake, pandemic, prolonged power outage
- Impact: regional outages, possibly loss of personnel, physical damage
- Immediate measures: safety of employees first, evacuation of the site where necessary, activate emergency workplaces
- Recovery strategy: geographically distributed data centres, cloud failover, home-office capability, alternative sites
- Specifics: file insurance claims early, communication with the local crisis teams
4. RTO/RPO per service class
RTO (Recovery Time Objective) is the maximum acceptable recovery duration, RPO (Recovery Point Objective) the maximum acceptable data loss, measured as the time between the last backup and the incident. How the values are derived from the business impact analysis, set below the maximum tolerable downtime and approved by management is described in the BCM guide in the section Defining RTO and RPO.
| Tier | Description | RTO | RPO | Examples |
|---|---|---|---|---|
| Tier 1 | Business-critical | ≤ 4 h | ≤ 15 min | Core ERP, control systems, online shop, patient record system |
| Tier 2 | Important | ≤ 24 h | ≤ 4 h | CRM, email, accounting, HR system |
| Tier 3 | Standard | ≤ 72 h | ≤ 24 h | Document management, intranet, internal reporting tools |
| Tier 4 | Non-critical | ≤ 1 week | ≤ 1 week | Archives, historical data, test systems |
The tiers are a practice example. In its example matrix the BCM guide sets, for instance, an RTO of 1 h for an online shop; which tier a service receives in your organisation is decided solely by your business impact analysis.
Technical implications per tier
- Tier 1: synchronous replication, active-active cluster, hot standby — costly, but necessary for availability-critical systems
- Tier 2: asynchronous replication, warm standby, fast restore from a current backup
- Tier 3: daily backups (snapshot or cloud), cold restore possible
- Tier 4: weekly backup, tape or archive tier in the cloud
5. Quarterly tests and annual full scenario
Tests are the most important effectiveness control: § 30(2) no. 6 BSIG requires concepts and procedures to assess the effectiveness of the measures. The following plan is a practice recommendation, not a statutory deadline. It supplements the exercise rhythm of the BCM guide (restore test every quarter, tabletop exercise at least annually, live test every two years) with one focus per quarter.
| Quarter | Test type | Scope |
|---|---|---|
| Q1 | Extended restore test | Restore 5 randomly selected systems from Tier 1 and 2, check integrity |
| Q2 | Failover test | Failover of a Tier-1 application to the secondary system, measure RTO; every two years in live operation as a live test |
| Q3 | Communications test | Test the alerting chain and the reachability of the crisis team unannounced |
| Q4 | Tabletop exercise | Crisis team works through a scenario (e.g. ransomware), practising decision and reporting paths |
Annual full scenario
- Realistic scenario (e.g. total data-centre outage, ransomware with data exfiltration)
- Full activation of the crisis team and the recovery team
- Simulation of communications with the supervisory authority and the media
- At least four hours of exercise time, for critical environments also several days
- External observation (auditor, insurer, adviser)
- Record with findings, lessons learned and corrective-action plan
Test documentation
Per test: date, participants, scenario, sequence, findings, measured RTO and RPO values, corrective actions with deadline and owner. These records are at the same time one piece of evidence for the documentation obligation under § 30(1) BSIG.
6. Ransomware: the most important special scenario
For ransomware the DR plan needs its own technical safeguards so that the backup survives the attack. The basics of the 3-2-1 rule and types of backup are in the glossary under Backup Strategy.
- Immutable backups: backups that cannot be overwritten or deleted during the retention period (e.g. hardened backup repositories or object storage with deletion lock) — active malware cannot alter them
- Backup isolation: backup infrastructure in its own administrative tier (separate Active Directory tier), without a trust relationship to the production domain
- Air-gap backups: copies regularly disconnected from the network (tape, external media in a safe)
- Recovery hardware on standby: clean systems for the restart after forensic clearance
The procedure in an emergency — isolate rather than power off, forensics before the restore, reports, criminal complaint and management's position on the ransom question documented in advance (practice recommendation: do not pay) — is described in the Ransomware Recovery 72h plan.
7. Documentation and audit evidence
§ 30(1) BSIG requires compliance with the measures to be documented. The BSI can order individual particularly important entities to undergo audits, inspections or certifications by independent bodies (§ 61(1) BSIG) and can require evidence from other particularly important entities three years after the Act's entry into force at the earliest (§ 61(3) BSIG). Where facts justify the assumption that an important entity is not implementing its obligations or not implementing them correctly, the BSI can review compliance and take measures under § 61 (§ 62 BSIG). Operators of critical installations provide evidence of implementation at a time set by the BSI, at the earliest three years after they were first classified as such, and every three years thereafter (§ 39(1) BSIG).
For an inspection, the following DR evidence should be available (practice recommendation):
- Current DR plan (version less than 12 months old)
- Business impact analysis with service classification
- RTO/RPO matrix per service
- Test records for the last 12 months (quarterly tests and annual exercise)
- Backup concept with immutable component
- Crisis-team list, current and with 24/7 reachability
- Communication templates for supervisory authority, customers and media
- Lessons learned from actual incidents in the last 24 months
- Approval of the current version by management
Typical gaps are an outdated plan, tests only "on paper", roles not updated after personnel changes, missing immutable backups and a crisis team without 24/7 reachability. Such gaps are hard to evidence as an effective measure under § 30(1) BSIG. Infringements of the risk management obligations can be fined under § 65(5) BSIG with up to EUR 10 million for particularly important entities and up to EUR 7 million for important entities; only where total turnover exceeds EUR 500 million is a fine of up to 2% or 1.4% of the undertaking's worldwide total turnover possible instead (§ 65(6) to (8) BSIG). Management must implement the measures and supervise their implementation; if it breaches this duty, it is liable to the entity for culpably caused damage (§ 38(1) and (2) BSIG).
In Austria, § 45(2) and (3) NISG 2026 provide for up to EUR 10 million or 2% of worldwide annual turnover (essential entities) or up to EUR 7 million or 1.4% (important entities), whichever is higher. There, the risk management measures implemented must be submitted to the Federal Office for Cybersecurity by self-declaration within twelve months of the registration obligation arising (§ 33(1) NISG 2026).
The NIS2 Kit contains four Word templates in module 05 "Business Continuity and Crisis": Business Continuity Policy, Backup and Recovery Concept, Disaster Recovery Plan, and Crisis Management and Communication.
Frequently asked questions
What does NIS2 require for the disaster recovery plan?
Art. 21(2)(c) NIS2 Directive and, in identical wording, § 30(2) no. 3 BSIG require measures for "business continuity, such as backup management and disaster recovery, and crisis management". In Austria the same obligation is in § 32(4)(c) NISG 2026. The law does not use the term "disaster recovery plan" or the metrics RTO and RPO. Because § 30(1) BSIG requires appropriate, proportionate and effective measures and compliance with them must be documented, a documented DR plan with RTO and RPO values is, however, the usual way to evidence this obligation.
What is the difference between a DR plan and a BCM plan?
BCM (business continuity management) is the higher-level view of business continuity and determines which processes must keep running with which priority; disaster recovery is the technical restoration of systems, data and infrastructure. BCM defines the what, DR the how — in legal terms both belong to § 30(2) no. 3 BSIG, explained in detail in the FAQ of the BCM guide.
Which RTO/RPO values are appropriate?
As a practice example, four tiers have proved useful: Tier 1 (business-critical) RTO ≤ 4 h / RPO ≤ 15 min, Tier 2 (important) RTO ≤ 24 h / RPO ≤ 4 h, Tier 3 (standard) RTO ≤ 72 h / RPO ≤ 24 h, Tier 4 (non-critical) RTO and RPO ≤ 1 week. These values are not prescribed by law. The binding values are those from your business impact analysis, approved by management, which under § 38(1) BSIG is responsible for implementing and supervising the measures.
How often must the DR plan be tested?
There is no statutory test frequency. As a practice recommendation, one focus test per quarter (restore, failover, alerting chain, tabletop exercise) plus an annual full scenario with the crisis team has proved useful. In legal terms, § 30(2) no. 6 BSIG requires procedures to assess the effectiveness of the measures and § 30(1) BSIG the documentation of compliance with them; test records with findings and corrective actions evidence both. For operators of critical installations, § 31 BSIG (including systems for attack detection) and the evidence under § 39(1) BSIG are added, first at a time set by the BSI and every three years thereafter.
Is a cloud backup sufficient as a DR strategy?
No. A cloud backup is a building block, not a DR plan. It lacks the activation of the crisis team, the communications plan, the fulfilment of the RTO targets (restoring large volumes of data from the cloud can take days), emergency workplaces and the escalation to suppliers. The cloud backup belongs in the DR plan as a technical measure, but does not replace it.
How do I integrate ransomware recovery into the DR plan?
Ransomware is a scenario of its own in the DR plan. Its specifics are immutable backups as the recovery source, an isolated backup infrastructure, forensic preservation before recovery, the report to the joint reporting office of BSI and BBK where there is a significant security incident (§ 2 no. 11, § 32(1) BSIG) and, in the case of a personal data breach, to the data protection supervisory authority (Art. 33(1) GDPR), and the evaluation of the lessons from the incident. The Ransomware Recovery 72h plan describes the procedure phase by phase.
Must the DR plan also cover cloud services?
Yes. Large cloud providers have high availability, but regional outages occur with them too. The DR plan therefore needs scenarios for cloud outages: alternative region or alternative provider, local backup copies, offline working capability for critical functions and contractual provisions on availability and damages checked in advance. Under § 30(2) no. 4 BSIG the measures must also cover supply chain security, including security-related aspects of the relationships with direct suppliers or service providers.
Sources
- Directive (EU) 2022/2555 (NIS2 Directive), Art. 21(1) and (2)(c) (business continuity), Art. 23 (reporting obligations), eur-lex.europa.eu
- BSI Act (BSIG 2025, BGBl. 2025 I No. 301, last amended by Art. 8(1) of the Act of 23 July 2026, BGBl. 2026 I No. 226), § 2 no. 11 (significant security incident), § 28(5) and (6) (exceptions EnWG and DORA), § 30(1) and (2) nos. 2, 3, 4, 6 and 10 (risk management measures), § 31 (operators of critical installations), § 32(1) (reports), § 38(1) and (2) (management), § 39(1) (evidence by operators of critical installations), §§ 61, 62 (supervision), § 65(5) to (8) (fines), gesetze-im-internet.de/bsig_2025
- Austria: Network and Information Systems Security Act 2026 (NISG 2026, BGBl. I No. 94/2025), § 3a(1) (cybersecurity authority), § 31 (management bodies), § 32(4)(c) (business continuity), § 33(1) (self-declaration), § 34(2) (reports to the CSIRT), § 45(2) and (3) (administrative penalties), § 51(2) (entry into force 1 October 2026), ris.bka.gv.at
- Regulation (EU) 2016/679 (GDPR), Art. 4 no. 12 (personal data breach), Art. 33(1) (notification to the supervisory authority), Art. 34(1) (communication to the data subjects), eur-lex.europa.eu
- Regulation (EU) 2022/2554 (DORA), Art. 2(2) (financial entities), Art. 11 (response and recovery), Art. 12 (backup and recovery), eur-lex.europa.eu
- German Federal Data Protection Act (BDSG), § 26 (employee data protection), gesetze-im-internet.de/bdsg_2018